Hello Community,
I have created a data Shuttle upload workflow via One Drive.
I ran the flow and it uploaded the data from the source file to the target sheet in smartsheet.
Then, I added a new row in the source file and wanted to see if the target sheet will get updated. After I ran the flow again, the new row wasn't added in the target sheet.
Can anyone advise please?
Tags:
Answers
-
Go to your Data Shuttle and click on the Last Run Date, it will bring up a summary. What does that say?
New rows will also always be at the bottom of the sheet.