Asigning special dates in Time Line Display
What I try to make is: E.g.: There is a task for the time between Aug 5th 10 and Aug 18. On Sep 14 partner XY is required to be present in City AB. Is there a way to show the alert icon in Time Line Display linked to additional details? The notification is already possible and the message can be sent to appointed person.…
-
Moving rows and losing formulae links.
Hi there, I use smartsheet a lot to manage and track report issuing between multiple users. I regulary have problems when moving rows to enable organisation by priority and the cell links within the row change. I have to reapply the formulaes in certain cells which can be time consuming. has anyone else had this problem or…
-
New in Smartsheet: Gantt and Calendar Views on Reports, Better Update Requests, and More
Smartsheet’s newest improvements give you more power to choose the level of detail you want to share, both within and outside your organization. Send a project rollup to executives using Reports, now complete with Gantt and Calendar Views, or share a single row to an external collaborator for a quick status update with…
-
printing of reports
hi..it looks that the printingioption and other indent icon have disappeared after an update today...do you have the same issue ?
-
Changing default message in task update request
Hi. I would like to change the default message from: "Please update the following rows in my online sheet" to a different message. How can that be done for me only or the entire account ? (both options ok)
-
How to send a notification to a selected recipient
How do I get SS to send a notification to a contact whose name has just been selected from the list and entered in a webform? Like, when column [supervisor] is set with a particular name, please notify [selected supervisor] of this change.
-
Task duration over a longer time frame, not consecutive days
I often have tasks that I know how long they will actually take to do, but just need slotting in amidst other works eg a 2 day job, but it needs to be within the next 2 weeks (10 working days). So it may be worked on 1 day in the first week and 1 day in the next week. If I enter the the period it can be done over, using a…
-
Calendar View
Is there a way to hide the weekends from my calendar and Gantt chart.
-
Best Practice for Backing Up
My project management team joined Smartsheet about 6 months ago and have created quite the plethora of sheets. All of them are in use as we are managing a very large project, so I do not want to delete any (and as we have so many paid users, we are far from our sheet limit) and they are all dynamic/active sheets. However,…
-
Symbols suggestion...
Okay - so mostly in jest, but a few of us would love a "Whack-a-mole" type icon to put on the rows of a few who are forgetting to get their project updated. Just wanted to toss that out there for others who might have the same problems - wer'e in this together, folks!! SOLIDARITY FOR SMARTSHEET!!!