Hello, I have a large multi-year project tracker. We have a manual select Risk column, where users will select the field should they anticipate a risk for the deliverable in question. I want to create an automation where when "Risk" is selected an automation is created to copy the entire row to a new sheet where the risk…
Hello fellow Smartsheeters, I am trying to capture entries from a project level RAID log and pushing them (based on specific criteria) to an Enterprise level RAID log. Specifically, any Risks or Issues that are created and updated need to be pushed to another sheet. I am familiar and frequently use the Copy Row Automation…
Hello everyone, In some fields in my sheets I have formulas. Is there a way to automatically report these formulas when I add new rows? Thanks
As of now it is only possible to assign a group of users to the blueprint of whenever a new workspace gets created for a new project. My idea is that there would be a possibility to automatically include the requestor of the project to the workspace, instead of the whole group. Perhaps it could be as follow: User requests…
This discussion has been merged.
Hi Community, I created a very simple automation where the trigger is when my % Complete row changes to 100% I want the Status cell value to change to complete. However it does not seem to be working. When I tried to run the workflow manually it changed all of my statuses to complete even if the % complete is less than…
Hello everybody I'd like create a workflow to copy the value of a cell date type when it changes to another cell in the same sheet. I can trigger the workflow when there's a change, however I can find a way to bring this value to the other column without using DataMesh or Formulas. In my case I want to avoid to use these…
for example if the status says in progress i want the %complete column to automatically say 50% can anyone help me?
I'm brand new to Smartsheet Forms and I'm on deadline. I accidentally created a Form tied to the wrong Sheet. After realizing my mistake, I duplicated the original sheet and fixed the new column headers (which had populated when I created the Form, of course!) and went back to the original incorrect Sheet ... I THINK it's…
We are managing a portfolio of projects that cut across multiple teams. Each team has a "spokesperson" that is responsible for completing a handful of reviews each month for portfolio governance, such as: Review report showing project milestones that they own Review report showing project milestones that are owned by other…