I am looking for suggestions and what other users utilize for an overview of all current projects within Smartsheet to prioritize and schedule. A summary report with a Gantt chart is just not sufficie…
Hello Smartsheet Team, I have been using Smartsheet for over a year now and my organization benefits greatly from Smartsheet functions! However, resource allocation is something that prevents us from …
Does Smartsheet allow for integration with Access database tables? Is this something that a connector is needed for; such as Data Uploader? Will the integration work with older editions of Access or o…
Has anyone had any luck with using API's or exporting/importing Smartsheet scheduling projects to Oracle Primavera P6? We are using the cloud version of P6 and both it and Smartsheet technically have …
Currently, I have a project template that I use for opening a new location. Our company is typically working on 5 or more location opening projects at a time. When changes need to be made to the basic…
I'm using this formula suggested in another thread to calculate the percentage complete for particular tasks: =(Today()-StartDate)/(EndDate-StartDate) What I'd like to know is how to cap this at 100% …
Hello, Is anyone else disappointed in the pricing and the lack of availability of the Smartsheet Addons/Premium Features? The features of these premium addons are pretty badass and would be useful. I …
Hello, What is the best way to "push" rows of data from multiple trackers into one tracker? Suppose user 1 and user 2 and a Manager use their own trackers. The trackers follow the same template. User …
Hello I have searched through the Help centre (center!) and I can't find the formula (if one exists....) that will automatically select the appropriate value in the % done when one of 6 choices from S…
Hi! I want the Parent row to automatically change with the most recent Child Row status. I currently do this manually so I have to update the status in 2 different rows. Right now I have this: =IF(COU…