-
Can I hide predecessor lines in a gantt chart?
I have a complicated project with tons of predecessors. The predecessor lines connecting tasks in the gantt view are so numerous that is makes the gantt visually hard to use. Is there are way to hide or turn off not the predecessors, but the predecessor lines? Thanks!
-
Duplicate Check
Hi, I want to identify rows that have a duplicate entry in a column entitled "Bill Number". How can I create a workaround formula to notify me when there is a duplicate? I believe the best way is to use a checkbox column entitled "Duplicate" and conditional formatting, but I don't know how to write the formula to check the…
-
Formula to collect resource's start date
Hello, I am trying to create a formula that will collect the min. date for the resource listed at row for various projects. If the resource isn't listed as a task owner, Right now, I am getting a blank response instead of my initial start date for a project. Current Formula: =IFERROR(IF(CONTAINS(Resource@row, {Task…
-
Auto Fill with Dates if certain category is selected
I am trying to figure out how to have certain cells auto fill with a generated date if a certain category is selected. Example: If "communication" is selected, I need a cell to auto fill with a date that is a week earlier than the "due date" column. Is there a way to do this? Thank you!
-
Big Time Saver: You Can Now Add Page Permissions in WorkApps
Hi Community, Are you tired of having to manually go into each role and set individual permissions whenever adding a new page to WorkApps? Not anymore! Smartsheet’s new features now allows users to set permissions whenever they add a new page in WorkApps, reducing the number of clicks it takes to change role settings as…
-
Date Modified
I have a sheet with a list of assets. There is a pull down menu that defines the status - I need to know when the menu is set to "complete". I can do that easily with a filter - but I want to cull the entries before a specific date. I have a Report that uses the 'is greater than-date modified' but I get results from all…
-
Estimate Date Planned against the target date
I need to calculate the planned date against the Go-Live date for each column. The dates are above the columns that should be prior to the Go-Live Target which is 10/31/22. I need to make the actual columns cells yellow for 3 dates against the planned date, red at the planned date. If a date is entered in actual column,…
-
Count time between dates in Weeks/Days
How would I calculate the time between two dates (start and finish) in Weeks and Days "8weeks 4days"
-
Match all columns to complete
I have several columns with dropdown (Complete-Go, Incomplete, TM Approved-Go) and one column that says (Go/No Go). If all columns have "Complete-Go or TM Approved-Go" the column (Go/ No Go) should be "Go" If any column has "Incomplete" the column (Go/no Go) should be "No Go" I appreciate your help very much! Rob
-
How to put a value for each item in dropdown list
I have a dropdown list and I want to put a value for each item (but not in the list): Not Ordered = 0% complete Ready to Order = 1% complete Order Process = 20% Shipped = 50% complete In Country Customs = 80% complete Delivered = 100% complete Cancelled = 100% complete This is to help me to calculate the task % complete…