-
Formula Help!!!!! PLEASE
I have a data set with a bunch of dates 09/03/19 09/04/19 08/19/19 07/01/19 You get the idea.... Im trying to get a count of "incidents" by month... but I cant get the formula to work!!! July = 10 Ive tried... (below) and many others... =COUNTIF({(NEW) Support Request (USER) Range 10}, MONTH({(NEW) Support Request (USER)…
-
User attachments
Hi, My team members are unable to attach files under the Individual Plan. According to the Smartsheet features attached, I should have this feature on my plan. Thanks, Kyle
-
pdf and excel files into multiple sheets via Gantt?
Hi there, trying to make a production line more efficient and I need to attach a file to each order (each order is a separate row). We run off of multiple sheets, and have reports broken down to each department. For example: Main Sheet: Gantt Production - includes all orders (which are linked to multiple reports) Report:…
-
Getting Status of Children to roll up to Parent Row
I have Parent tasks with Children tasks in a dropdown list column. The options for the children are: assigned, in progress, complete. would like to have the parent status display be blank if none of the children have a status selected (all are blank), display "Complete" only if all the children have a complete status,…
-
If Current Month
Hi I'm trying to write a formula that will show me a column for the current Month Currently formula =If(Month(date column)= 9, [Project]1)- This works and displays the correct cell, however I want the column to change with the month so I tried= IF(Month(date column)=Month(Today()), [Project]1), I get an error Any…
-
Duration Vs Project Days
I have a project where the planned tasks are spread over several weeks, see attached. How is the summary % complete total calculated? Can I relate to %complete against project days? Regards Steve
-
Project Time in Minutes vs Days
Has anyone tracked a project by minutes vs days? Goal of the SmartSheet project is to create a software upgrade by minutes vs days. Issue: The software upgrade typically takes 2 to 3 days. The upgrade schedule is by minutes and resources and task need to be schedule by minutes to plan the time the system will be down.
-
Formula with multiple IF criteria
Hi all - Trying to create a formula that raises a flag any time a milestone is NOT marked complete AND the due date has past. Below is what I have tried and I am receiving an "Unparseable" error. =IF(Stage2<>"Complete" AND [Due Date]<= TODAY, 1) I am not sure that I am combining the two statesments correctly. Can anyone…
-
Automatocally changing due dates and status on recurring tasks (Monthly, weekly, etc)
How do I make a row update the due date for a monthly, weekly, and/or quarterly recurring task? I would like it to automatically change the due date to one month, one week, or three months in the future and change the status back to Not Started once a recurring task is marked Complete. I need to be able to do this at the…
-
SmartSheet Recent Update - Attachments/Versions
With the recent update to SmartSheets, our company has seen a few issues. The first issue has been the version numbers. If you look at the example below, the version numbers are out of order. We deal with a variety of freelancers that don't work for the company, but rely heavily on the version numbers. Now with them being…