Need help getting multiple sheets pulled into a single report in the correct order
I have three "what if" schedules that I'm trying to pull into a single report. They are simply named Scenario 1, Scenario 2, and Scenario 3. No matter what order I select them, the resulting report has #3 in first position, #1 in second, and #2 in last. I did a bulky workaround by adding a Helper Column in each sheet…
-
Receipt for Work Completed
I want to auto generate a receipt with Zapier or something and send it to the supervisor and client upon work completed. Problem: Our electricians perform tests on all equipment we install. We have many QC forms that we use but using them is very cumbersome. Our techs need to ensure that they print them off before going to…
-
Horizontal Axis Maximum Range
Does anyone know how to alter the horizontal axis range? I have a chart that is displaying percentages but the horizontal axis maximum percent is set to 120% so pieces of the project are looking as though they are not complete. I tried stretching the chart out and making it smaller, nothing works. In excel you usually have…
-
Can I reference the workspace in a sheet or report?
I have a report that compiles data from multiple Workspaces. I would like to be able to include the workspace in the report as a column (just like I can include Sheet Name as a column.) Is there at least a formula that I can include in a sheet that returns the name of its workspace? e.g like =WORKSPACE() ..?
-
Feature Request - Comments and Attachments trigger 'modified' column value
I'm trying to create reports that will show my projects the changes to their workspaces over the past day. I thought a report would do the trick, and I'd just filter by modified within the last day. However, reports don't always catch what you're looking for, like ALL the changes. Report WARNING, the "modified" system…
-
Last Modify Date based on Comments
I'm looking to see if there is a way to update the "Last Modified Date" system column when someone adds a comment to a row.
-
Trigger Report Due when month changes from modified date
Hi I have a basic text entry sheet for a dashboard report. Fields are: [Subject], [Details], [Modified], [Due] In the [Due] Column I want to show that the month has changed so I can trigger an update request. How would I go about doing this? Regards Steve
-
How to add a Red Flag when there is an entry more than once in last 12 months
Hi, I have a table which records driving infringements. What I want to be able to do is have a function determine if a driver has had more than one infringement in the last 12 months. Then use the Actions and Alerts to notify their manager. But need the function to work first before I can do that. I know how to use the…
-
Raise flag if due date is within 30 days
Hi There I'm very new to smartsheet so for you this might be a very simple thing. I'll appreciate if someone let me know what'd be the formula if I want to raise a flag whenever the due date is 30 days from the current date. We'll appreciate your help. Thanks Raashid K
-
Card View is great for sheets. Please bring to reports, too.
Love Card View! I can definitely see using it. My issue is that I do almost all of my viewing in Reports as opposed to Sheets because I work across many sheets for my work, consildated into Report views. I know there might be complications to implementing this, for example when a sheet included in report does not have a…