Smartsheet's Error in % Complete Rollup
Hi,
I recently realized that Smartsheet has a major flaw in rolling up % Completion.
In Smartsheet %complete for a Parent is calculated as a weighted average of %completion of the immediate children times the duration of the Parent. For example in the following Project, the overall % complete shows 50% where the correct % complete is 10%: Completed work (1 day) divided by total work (10 days) equals 10%.
In other words, task1 is overweighed and all subtasks under task 2 are underweighted.
I have escalated this to smartsheets and would like to share with the community as this could have serious impact if you are managing a complex project.
Cheers,
Mahmood
Comments
-
Hello Mahmood,
your project has two tasks. Each of the task lasts for 1 day, so if one task is done you have 50% of your work done.
If the subtasks would not all take place on the same day but one after another - shown in "Project 2" - task 2 runs for the sum of the tasks and then the calculation shows a reduced value, as you expected.
Best
Dietrich -
In that case samrtsheet calculates "%duration completed" instead of "%work completed". In my example I wouldn't consider the project 50% done in the beginning of second day.
-
Thats how Smartsheet works. Here's what the Smartsheet Help says to %Complete:
"... In parent (summary) rows, the % Complete is calculated automatically by Smartsheet based on both the Duration and % Complete values you've manually entered into the child rows."
Best
Dietrich
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!