I usually set allocations rates as average during term.
But,When the task is long term, it is different allocations rate at each point in a same task.
And if I set allocations rate to another task at low loard point,Smartsheet alert the over resource by caliculating rates.
(Because of the allocations rate is average during term.)
It is timeloss to adjust the schedule in every time when Smartsheet alert that.
So,I want set the different allocations rate at each point in a same task.
If someone has good way to solve,please advice me.