Update request missing option to change end dates
Hello,
I'm a rookie to smartsheet and PM work. I have sent out my update requests and my partners on the receiving end are telling me they cannot update the end date field. They are able to edit every other field. Can you help?
Does it have something to do with changing the end date of the parent row first?
Thanks!
Monica
Comments
-
Hello Monica—end dates used for dependencies can't be changed via update requests. This is mainly because the person submitting the update via the request doesn't have context for the other tasks that can be automatically pushed around based on the end date they set or change.
More information on update requests can be found in our Help Center: http://help.smartsheet.com/articles/504779-using-update-requests
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives