Setting different working days for individuals
Is there a way to set different working days for individuals? I know that it is possible to define working days through the Project Settings function but I want to set this for one person only to reflect their part time working structure - is this possible?
Any advice would be gratefully received.
Thanks
Popular Tags:
0
Answers
Hi Harriet,
At this time it's not possible to set up specific working days per-resource or per-person; as you've found, you can set working days for the Sheet in the Project Settings, but this will apply to the entire sheet/project, not just to one individual. (Please submit an Enhancement Request when you have a moment!)
Depending on how your set up looks, you could potentially set up your project to have different people with their own specific sheet/working days, then use a Report to pull together specific information across these sheets.
Alternatively, you may want to look into 10,000ft as a resource management software for tracking working days & individual workload.
Cheers!
Genevieve
Ok thanks