Vertical line in Gantt - Data Date
It would be great if there was a way to add a drop line on the Gantt view i.e a vertical line that communicates important information like the data date i.e the date the schedule was updated These visual tools are important for consultants when trying to communicate data to clients etc
-
Ability to "postpone" a successor task.
If I am working on a schedule for a new equipment installation generally I will have to get a quote, then wait for the quote to arrive, then submit it for Capex approval, then wait for approval, then schedule the installation, then wait for equipment delivery, and then finally installation and commissioning. Preferably I…
-
Timeline View - Enhance Space for Milestone/Task naming
Dear Community-Members & Smartsheet Development Team, The long-awaited Timeline View feature was recently released. It is a very good feature to use for visual data sharing of timelines (ex. screenshots for presentations). However, we quickly realized in project management that a large number of names are cut off in terms…
-
Smartsheet Gantt Chart
I’d like to suggest enhancing the Gantt chart to support more complex project schedules, similar to Microsoft Project Professional or Primavera P6. Currently, Smartsheet’s Gantt chart works well for simple schedules but is not suited for managing complex construction projects. Improving this feature would make Smartsheet a…
-
Unable to use formula based date column in gantt/timeline
Any workarounds welcome. I'm importing some task data using Data Shuttle. The task data includes Created Date, Start Date, End Date. We want to use a column formula to set the start date (if its empty) to equal the Created Date. Easy enough.. I renamed the incoming Start Date column and added a new Start Date date column,…
-
Conditional Format For "Task Bar" independent of "Entire Row"
My use case I have rules for various rows based on the Issue Type and I want a rule for the Task bar based on the status of the issue. For example, I want an Epic to show up with a Grey background, but I do not want the grey background to extend into the Gantt Chart but I want the Gant chart to show up as Green if the task…
-
Gantt Chart - Percentage Complete
Hi, I'm new in Smartsheet coming from the MS Project world. I'm trying to include the % of task completion in a gantt chart. I'm filling in the % complete column but nothing appears on the gannt chart (contrary to what is described in…
-
Fiscal Quarters in Timeline View
It would be great to have user definable fiscal quarters in the new Timeline view. Also, as I am creating this discussion, there isn't a tag for Timeline View yet 😁
-
Merged: Linked Non-Working (Holiday) List
This discussion has been merged.
-
Would like the Report Gantt View to grey out days off
The Gantt view in a report would be much easier to view, and use if the days off were grey. It's like this on the source sheet. All the info I can find is for modifying the gantt in a sheet, not a report. Is this possible?