Hi,
I have a planned date column, and I would like to send out an update request to the contact column when the planned date is = to today.
Is this possible?
Thanks,
Aaron
Yes, this is possible as long as you have the correct plan. I believe a Business or Enterprise Plan is required in order to send Automated Update Requests.
Do you know what type of plan you have? If you're unsure, let me know which of these tabs you can/cannot use at the bottom of your sheet. You would use the "Alerts & Actions" Tab in order to create this Update Request.
If you don't have a business or enterprise plan you can send out a reminder based on that date and customize your email asking them to update the information on the sheet. It doesn't send the update email, but it can work as a reminder to them to do the task.
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…