I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
Hi. Goal1: For project management purposes, I am trying to compare project "Current Start Date" column in one Smartsheet (SmartSheet #1) against a "Q2 Start Date" column from another Smartsheet (Smartsheet #2). This is to compare the latest/daily Current Start Date against the Start Date that was planned in Q1 for a list…
Why can't i copy a text message that was posted in the Conversations tab? Did this change with the last update as i was always able to do it?
Hello, I have a report that summarizes all hours spent on a particular phase. Is there any way to include the missing information? I need to create a condensed report to add to a dashboard. Missing information: Site Name, Turbine Number, Blade Number, Date Performed, & Current Phase