I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
I HAD A MOBILE APP THAT WAS RUNNING FINE UP TO THE LAST TWO WEEKS. IN THE LAST TWO WEEKS NOW THE NOTIFICATIONS ARE NOT APPEARING. THE APP KEEPS BUFFERING BUT NOT SHOWING THE NOTIFICATIONS ON THE MOBILE PHONE APP HOWEVER I CAN SEE THE NOTIFICATIONS IN THE DESKTOP APP.
Is it necessary to have a predecessor for the critical path to work? Because when I set a longer duration, it stops considering the critical path in the other tasks with a sequence and only shows the one with the longest duration.
Card/Board view doesn't show Assigned To column as an option for grouping items. Some possible causes that I've already checked: There are no rows that are empty in the Assigned To column Rows with multiple assignees have also been converted to one assignee only The Assigned To column is of the Contact type The assignees…