Non-work Weekends For Only Some Rows

Hi Smartsheet-ers,
I'm looking to organize a project sheet that has some task rows that work can happen on weekends, and some task rows that the work will not happen on the weekends.
We work with two staffing schedules. A portion of the staff working on the project work on weekends, while the others do not.
Does anyone have way to implement this in a project Smartsheet?
I'm looking for an automatic way vs. manually adjusting the lag days when needed to eliminate potential errors in adjustments.
Thank you!!
Tom
Comments
-
Hi Tom,
There currently isn't a way to apply non-working days/holidays on the row level. When you have a moment, submit a product enhancement request using the form under Quick links on the right to let our Product team know that you'd like to have this functionality in Smartsheet.
-
I found an article that may solve this for you, using the elapsed time indicator in the duration column. Here's the article:
https://community.smartsheet.com/discussion/17951/independent-work-days-for-tasks-or-resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.5K Get Help
- 468 Global Discussions
- 156 Industry Talk
- 511 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 520 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives