I am wondering if there is a reason why my update request will not let the user update % Complete. Does anyone have any insight to why it will only allow certain things to be updated?
The way the Request is set up is: "On 03/04/19 at 11am In any row where % Complete is less than 100% and Start Date is in the past Send an update request to Assigned To."
I went into the advanced options at the bottom of the request and adjusted the Column Visibility to display excatlly what I wanted. But I just can't figure out why the request doesn't allow the update of % Complete.
Also, I do not have the column set to LOCKED or FREEZE.
Comments
-
Is there a formula in the column? Is your percentage updated via a formula? If so, that will block editing in an update request.
-
The % Column is manually updated. I think the problem was how I was sharing the sheet, I had the recipient set to" Viewer" so I switched it to "Editor-cannot share". I will see at noon if this has fixed the issue.
-
Yes, that would also cause issues. Let us all know if you figured it out.
-
I did get this figured out. It was literally something so simple. I was using the parent task as my test run, and you can't change the % Complete in a parent row. So thank goodness it was an easy fix!
-
Haha. Yes, that makes perfect sense.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 59 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives