Hi,
I have an action plan with an action column, a delay column, a referent column, and a progress column.
I would like to create a workflow that sends a notification (mail) to the referent of the action 3 days before the date entered in the column "delay" if the progress is not "finished" in order to remind him to finish the action.
This is my trial, but it sends notifications only for actions that have a deadline = to the current date
Translation :
Statut = progress of the action
Délai = delay
If somone have the solution, thanks !
Comments
-
Hi Thibault,
You were almost there!
- If you change on after Run once to 3 days before
- Delete the second Condition
That should work.
Did it?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi Andrée,
It works, thank you for your message and sorry for my late feedback.
Regards.
-
Excellent!
Happy to help!
✅Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 67 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives