We have multiple projects ongoing simultaneously. In each project tasks are assigned to various team members by the managing partner. Is there a way to have a task automatically roll into a master tas…
I see in the API documentation that the programatic access of row data in columns of type Predecessor, Duration, etc. is not supported. I'm doing what I've seen many others on this forum try to do; I'…
We are currently running multiple Projects and have setup a Master Folder with our Process Task lists in using Card View. Within Card View we have links to some Webforms used to capture Data for certa…
Im new to this. If we have one resource alloocated over several sheets and in one sheet/project the resource is required for an extra day, How do we link so that all associated sheets dates are update…
Is there a formula to determine percent complete of a task based on the cell color? Cells are filled with dates of various steps in a project and once those are completed, the cell is highlighted. I'd…
Hi all, I'm getting NaN% appear on my sheets where that cell is linked to another sheet. The source cell appears OK, and I've tried remaking the link, but no affect. Is this the 2000 links I'm running…
Hello - I'm trying to put a summary line at the top of my sheet showing the latest date on the critical path, so that i can view it even when all the sections are collapsed. Is there a way for me, in …
I am working with 2x sheets - one a CRM, the other a job list. I would like to be able to flag on the Job list when a customer name is entered which is not already in the CRM. In Excel I could use a c…
For large sheets, is there a way to link from rows to other rows within the same sheet. For example, I have developed a lirbary of sorts with files that fall into different categories. There are sever…
I've been assessing Smartsheet as a viable replacement for MS Project at our office over the last 30 days and I thought I'd share my finding with the Smartsheet community in case somebody else is also…