-
Is there a way to set a constraint on a task's Start Date that can override a predecessor?
We have migrated a fairly complex plan from MS Project to Smartsheet and have been able to line up most of our dates. However, when Predecessors finish early on a task, the start date is impacted, as expected. In MS Project we can use constraints to say the next task cannot start early even if its predecessors end early.…
-
Trigger a monthly approval automation?
Hi there, A team keep track of hours worked per project on a sheet that looks like this. I'd like to trigger a workflow that sends the project manager an approval request on the first date of each month to approve the work completed the month prior. However, I do not want the project manager to get separate emails for each…
-
Add Latest Comment Column without creating a comment
When creating a Grid, need the ability to add Latest Comment in Grid view without having to add a comment first. Thank you.
-
Copy/ Paste Cells With Multiple Lines Doesn't Work
I've been digging through community for resolution to this issue, but I'm coming up empty. I need to be able to copy/ paste multiple rows of data that have "multi-row (alt+enter)" information from Excel (and Smartsheet). Currently, when I try to copy and paste these "multi-row" cells, they spill into separate cells instead…
-
Pivot Table Like UI For Creating Metrics in Sheet Summaries
In Excel you can customize formulas and drag and drop the information you want int Rows, Columns, Filters, etc... via Pivot Tables to build data points and summaries of large amonts of data. If we could bring this functionality to Smartsheet's Sheet Summary with the help of the recent LLM functionalities implemented for…
-
Alert/Notification when line item hasn't been added
I am building a sheet in which 6 managers provide updates in the form of line items. Each week our Director reviews this sheet for the latest updates. I am looking to create a notification system that would go out to each manager that doesn't provide at least one update (add one line or modify an existing line) in the last…
-
Is there a way to delete a cross sheet reference?
I had a working formula referencing another sheet. It was referencing a set of cells in a column. I changed it to look at the entire column and started getting an #Incorrect Argument Set message. I tried to change it back to the range of cells and I'm still getting the error message. I wanted to delete the cross sheet…
-
Average symbols for growing number of columns
Hello all, I know this is likely possible, but I've been struggling to think of the most efficient process. Below is a sheet I'm working on, where trainers enter progress for a trainee in a given "soft skill." These trainer columns will be added automatically on a daily basis via an outside Power Automate flow, while the…
-
Streamline Sheet Reference Manager
I just went through an update where I needed to manually add 3 new sheet references to 26 Stakeholder Registers (78 total). I wish that after you click Insert Reference, the Sheet Reference Manager dialog box would remain open.
-
Cross-Referencing Assigned To Error
I am building out a roll-up sheet and have everything working nicely, with the exception of a single formula. The part of this sheet I'm having trouble with is in the image below. What I am trying to do is have this sheet look at the person named in the column "Primary", then check a couple other sheets to see how many…