Tracking Assigned Tasks

Dears,

 

How to view a specific person tasks on smartsheet, i assign multiple tasks for multiple users so what is the best way to keep informed or to check the update of a specific person tasks.

 

Thanks.  

 

Comments

  • JamesR
    JamesR ✭✭✭✭✭
    edited 11/05/15

    Create a report for each person so that it only shows thier tasks.