-
pdf and excel files into multiple sheets via Gantt?
Hi there, trying to make a production line more efficient and I need to attach a file to each order (each order is a separate row). We run off of multiple sheets, and have reports broken down to each department. For example: Main Sheet: Gantt Production - includes all orders (which are linked to multiple reports) Report:…
-
Remove Predecessor Link
I accidentally drug a line to link two tasks, they are not dependent on each other. How do I remove the predecessor line?
-
highlight today's date
I've just begun using SmartSheet and like it a lot, but it seems as though my team and I keep running into the same problem in various contexts when using Gantt view. Specifically: It's hard to find today's date. Every time we open a sheet, we first need to make sure we KNOW today's date, and then we spend a couple of…
-
DataMesh & Gantt Charts
I am working on a project that we are trying to DataMesh two individual Gantt schedules into one new worksheet together. I've not DataMeshed too much, but is this possible? I use a formula of "Row # + Site #" as my unique identifier for the config. I set up the config, and the first time I kept on getting errors, so I…
-
Forced dates when dependency is enabled
We are working to importa 1800 line project plan into smartsheet and have run into a dabilitating problem with the dates. What looks to be happening is that the “Duration” and “predecessors” fields are completely driving the dates for the tasks. Anything with a predecessor is automatically forcing the start date to be the…
-
Best Formula
I have a construction schedule with start and finish dates. I want the check boxes for the at risk column to automatically check off if the project is late starting or late finishing. Can anyone help me craft the appropriate formula for this? Is there a good formula for this? I was thinking it would be an if then formula…
-
Look up blank cell and add a value in another column on the same row
Can someone show me how to write a forumla that will look up if a cell in the column "Critical date" is populated enter 1 in column "CD2" on the same row. Essentially what I'm trying to do is run a report that summarises all my critical dates but I can't select that date column in my report. If there is a better way I'm…
-
Gantt chart timeline settings
I have admin access and have set the Gantt settings on a particular sheet to Primary heading: Months Secondary heading:Weeks I have shared the sheet with another user and given them Editor - can share permissions but they are seeing a different view on the Gantt chart. Why is that? What do I need to do for them to see the…
-
Resourcing is looking at SCC template gantts
Firstly, yes - I know the Control Center sheets are not "templates" but I would want resourcing to be able to filter out the workspace or at least the folder used to spin up SCC projects. Since I pre-load "assembly time" by assigning it to the genaric "Assembly" contact in ALL of the grouped gantt schedule options (of…
-
Gantt View - Settings requests
Hi, I'm trying to create a dynamic 'To-Do' list (for want of a better phrase), that automatically steps the jobs - i.e. only start task 2 when task 1 is expected to complete. I want to make this as automated as possible, and I understand that dependancy columns do not accept formulas, but wanted to know if there was…