To sync Status column in Smartsheet with Resource Management.
The Smartsheet integration with Resource Management should provide fully sync of column in Smartsheet task list. Currently only the column "Task, Assigned to, Allocation Hours, Start Date and End Date" are sync to Resource Management. One of the purposes of integration should help in maintaining up-to-date project statuses…
-
Filter Resource Management Timecard
Our team enters time in Resource Management to many projects. Sometimes 1 person has 10s of projects they are assigned so it makes the weekly timecard rather long and hard to update. The idea is for there to be a filter in the side panel where the user can filter on Projects or Grouips of Projects by client so they can…
-
Ability to "postpone" a successor task.
If I am working on a schedule for a new equipment installation generally I will have to get a quote, then wait for the quote to arrive, then submit it for Capex approval, then wait for approval, then schedule the installation, then wait for equipment delivery, and then finally installation and commissioning. Preferably I…
-
Resource Management analytics report to show phase dates
We'd like to run a Resource Management analytics report to show phase dates. Currently, it only seems to show the total project dates, but the data is there in the project.
-
Visibility of where rows moved too or from in activity log
In the activity log when rows are moved either too or from a sheet having visibility of the source destination sheet would be a great asset as in the workspace there is a large number of Sheets updated daily and several admins.
-
Improve Clarity Around Run Now Automation
Despite the text that tries to explain this, I don't think the current documentation for the Run Now feature is clear to new users. What isn't clear is that the Trigger and initial Filter condition are treated together and both will be ignored when using Run Now. Besides the help text description, the visuals for this…
-
Milestone in Timeline View
Hello support team, when we switch from Grid View to Timeline View, we can only see one time bar per line. The time bar has a start and end depending on the columns selected in the Settings and if there is only one date specified we see only one Milestone. It would be extremely helpful (and I guess fairly simple to…
-
Logo on Forms
My logo is tiny but can't be adjusted. Make Logo size adjustable on Forms.
-
provide ability to add links in a Form
I have a case where when the user opens up the Smartsheet form, if specific conditions are met a link to a file should appear. Currently this is impossible to do. either provide the ability to easily put a link in a field within the form OR embed a form within a form would be ideal. With the link option, we should be able…
-
Make URL to row attachment permanent.
I have a request from senior leadership to provide a link to the project charter which is attached to the row of the project intake sheet. This URL would be shown on the project review report that is sent to leadership for review prior to weekly project review meetings. I have created a BRIDGE integration that gets and…